Last week I said I would:
- Plan a communications meeting for my newly enlarged team (planning started - but it won't happen until week after next)
- Help all of my team get PBC goals written up (partly done - mine are agreed, but many of my team have not yet finalised theirs)
- Finalize the plans for Portal and Mashup Maker to move to the latest Sametime API (Portal plan nearly finalised, but Mashup maker not yet)
- Try to get a clear plan on Lotus Connections about how the two products can work together better (no real progress)
- Help with testing ST 8.5.1 on Linux - particularly Pulse Audio support (done - but ongoing)
- Discuss with Sametime team the possibility of changing the Sametime Linux kit build process and install process to match what has been requested by the Open Client team. (put this action on holdm because bigger issues to be solved)
- Continue using Notes as a GTD tracking system (done)
- Blog about using BlueTwitSidebar (done)
- Plan a communications meeting for my newly enlarged team (the following week)
- Write report on HR investigation
- Get get PBC goals agreed for all of my team.
- Help make plans for OSS Bar Camp
- Finalize the plans for Portal to move to the latest Sametime API and finalise technical direction for Mashup Maker integration
- Try to get a clear plan on Lotus Connections about how the two products can work together better.
- Help with testing ST 8.5.1 on Linux - particularly Pulse Audio support
- Set up Sametime 8.5.1 build environment on my PC so that I can learn more about Sametime internals
- Write a Q1 review on my blog
- Continue using Notes as a GTD tracking system (and write blog post about my experiences)
No comments:
Post a Comment